Jordan's Hussein power project connected to grid

Published 28 February 2018

SEPCOⅢannounced that the three gas turbines of Hussein Project were combined to the grid and commenced operations in Jordan.

At present, the commissioning and testing of project have beingcarried out in an orderly manner, and the hydrostatic test of all three wasteheat boilers have been completed recently.

During the hydrostatic test, thelifting and lowering pressure rates all met the design requirements, during thepressure regulation, there was no leak in the system inspection.

The systemremained stable during the overpressure, the pressure-containing members of theboiler body and the valve were not leaked, the pressures parts were notdeformed, quality of technology and other technical indicators have reached theASME technical specifications.

The project was highly recognized by owners,supervisors, equipment manufacturers representatives.

Source: Company Press Release